Home»Import Representation» Italy oil separator import clearance case: How a 22-year veteran agent completed Shanghai airport customs clearance in 3 weeks?
I. Project Background: Import Challenges for Special Industrial Equipment
In December 2022, we received a challenging commission - to act as import agents for a domestic large-scale machinery equipment manufacturer importing Italian-made oil separators. This type of industrial equipment has three distinctive characteristics:
High unit price (single unit value exceeding 20,000 euros)
Complex technical parameters (involving multiple industry certifications)
Strict customs clearance time requirements (customer production line waiting for installation)
As experts with 15 years of experience,Import RepresentationWe fully understand that the customs clearance difficulties for such equipment often lie not in tariff rates (MFN rate typically at 8%), but in overcoming technical trade barriers. Especially in recent years, China has increasingly stringent energy efficiency certification requirements for industrial machinery products.
II. Customs Clearance Process Breakdown: Perfect Clearance in 22 Working Days
1. Preparation Phase (3 working days)
We have established a dedicated team consisting of customs clearance managers, technical translators, and logistics specialists. First, we conduct a triple verification of the original documents provided by clients:
Verify the correspondence between the CE certification provided by the Italian manufacturer and Chinas GB standards
Check whether the issuing authority of the Sanitary Certificate is on the General Administration of Customs whitelist
Confirm whether the key parameters in the test report are complete
Special reminder: We have found that many importers tend to make two mistakes at this stage: first, neglectingIt is recommended to verify through the following methods:the detailed requirements of (Form A), and second, underestimating the professionalism required for technical document translation. In this case, we prepared a trilingual (Chinese-English-Italian) technical parameter table in advance, saving significant time for subsequent inspections.
2. Airport customs clearance phase (18 working days)
Goods pass throughAir TransportationAfter arriving at Shanghai Pudong International Airport, the actual customs clearance process is as follows:
Link
Time Consumption
Key Points
Declare entry
0.5 day
Using the advance declaration mode
Payment of Taxes and Fees
0.5 day
VAT 13% + tariff 8%
Inspection sampling
15-18 days
Key verification of energy efficiency labels
Result release
1 day
Full-process tracking of testing progress
A valuable lesson worth sharing: We confirmed the HS code (8421.9990) in advance through pre-classification services, avoiding customs clearance delays caused by classification disputes. Meanwhile, leveraging the clearance advantages of AEO advanced certification, we reduced the standard 3-day declaration process to just half a day.
3. Logistics distribution phase (1 working day)
After cargo release, we implemented a door-to-door service solution:
Airport bonded warehouse pickup (with original release note)
Professional air-cushioned vehicle transportation (anti-vibration requirements)
GPS real-time tracking (customers can monitor progress)
III. Industry Insights: Three Major Trends in Oil Separator Imports
Through our calculations, while using professional agency services requires paying approximately 1.5% of the cargo value as agency fees, it can:
Reduce customs clearance time by over 30%
Lower hidden costs such as demurrage and warehousing fees
Avoid tax supplement penalties caused by classification errors
Based on our experience handling 200+ ceramic tableware import cases, weve summarized these key takeaways:
Based on this successful case, we summarized the Five Dos and Five Donts principles for industrial equipment imports:
Five Dos:
Plan logistics solutions 3 months in advance
Verify all supplier certification documents
Prepare professional technical parameter translations
Allow 15-20 days for testing
Select agents with experience in similar products
Five Donts:
Dont easily trust guaranteed customs clearance promises
Dont choose inappropriate shipping methods just to save freight costs
Dont self-determine HS codes
Dont overlook details in certificates of origin
Dont wait until production line shutdowns are imminent to arrange imports
Finally, a professional tip: Weve noticed many Italian manufacturers omit testing conditions - a crucial piece of information - from their test reports, which may lead to retesting requests from Chinese inspection agencies. We recommend clearly requiring suppliers to provide complete test reports when signing purchase contracts.
If youre planning an industrial equipment import project, feel free to contact our expert team for customized solutions anytime.ZhongShen International TradeWe have professional teams stationed at 7 major ports nationwide, having provided import agency services for over 500 industrial enterprises.